Pedestrian Improvement Projects Update (May 20, 2024 through May 25, 2024)

York and Summit: Marino Corporation will be working at the intersection of York Road and Summit Avenue from Tuesday, May 21, 2024 through Thursday, May 23, 2024. Please note, there will be parking restrictions in the area as needed while work is taking place.

York and Williams: Marino Corporation will be working at the intersection of York Road and Williams Lane from May 21, 2024 through May 23, 2024. Please note, there will be parking restrictions in the area as needed while work is taking place.

Jacksonville and Meadowbrook: Marino Corporation will be working on Jacksonville and Meadowbrook from May 21, 2024 through May 23, 2024.

Please note, all work mentioned above is weather dependent and is subject to delay. Motorists are advised to avoid the area if possible to avoid delays in the area. All Hatboro Businesses continue to be open and operating while work is taking place. Please remember to shop small, shop local and shop Hatboro now and always.

For questions regarding this work schedule or the Pedestrian Improvement Projects, please contact Borough Hall at 215-443-9100.